Monday, February 10, 2020

Tape & Texture

This week we got an unexpected phone call. We just had a real cold front move in and our tape and texture guys are "frozen" out of their Beaver, Ut job. They asked if we wanted them to come finish our house. Ummm ya! That's a no brainer! 

So we had one night to hussle and get everything out of those front rooms again!
Kory decided to go ahead and hang up the lights in the master bath to help get rid of the clutter. 


Despite following the directions for the master tub our water was to far into the wall and the fixture wouldn't reach. So Kory had to cut a hole in our newly painted wall to extend the water. Our tape and texture guy will do their thing on this spot when they are here. 


We had to get all the stuff out of our front entryway. That meant our 2 refrigerators and deep freeze. Now they are all in the kitchen where one day they will find their permanent home.  


Our kitchen has a new look again. Just thankful its functional. 


I don't love the oven sitting in the middle of the floor but at least I still have one. It's been cold this week and we've been super busy so it's been nice to bake a pizza or throw in a freezer meal.   


On Tuesday they came and just taped the seams. 


On Wednesday they put the 2nd coat on the seams and covered the screw nails.  


On Thursday they textured the ceiling and walls. 


On Saturday morning they came back and sanded it so that we can start painting. 
Yay!!

During the week we worked in the master bedroom. Had to grind the floor and pour some more self leveling cement so that it will be ready for carpet one day soon. 
 

In the master bath we had to cut concrete for what I hope will be the very last time ever!
Had to find our bathtub drain. 

We got it all stubbed out and ready to install our bathtub. Just got to get the flooring done now. 

No comments:

Post a Comment

Master Shower

People keep asking what's left on the house?  The upstairs is 100% complete. Yay!! There are 3 things left in the kitchen, 1) Back splas...